LS Cable与LS Marine锁定韩国504 MW海上风电项目电缆产能与安装档期

作者:   发布时间:2026年11月04日    浏览量:8   字体大小:  A+   A- 

LS Cable与LS Marine锁定韩国504 MW海上风电项目电缆产能与安装档期
图片来自网络,版权属于原作者

来源:Offshore Energy 2026-11-04

翻译:国际海事信息网 李姿熠 张运鸿

 

        该协议在主合同签订前,为LS Cable & System的设施预留了制造产能,并为LS Marine Solution的电缆敷设船(CLV)预留了安装档期。两家公司计划在2026年底前敲定合同,包括合同金额及其他条款。

 

        两家公司于2024年被选为该电缆包的首选投标人,目前正在开展工程工作和初步勘测,以确定电缆规格和安装范围。

 

        Taean Wind Power是Copenhagen Infrastructure Partners(CIP)与Vena Energy的合资企业,双方正在开发该项目。该项目在韩国2024年风电固定价格拍卖中获得承购合同。

 

        2025年,开发商还与Korea Western Power和Gangneung Eco Power签署了覆盖500 MW的电力购买协议(PPA)。

 

        根据此前项目更新,风电场建设计划于2026年第四季度开始,商业运营目标为2029年第四季度。

 

        LS Marine Solution计划部署其GL2030电缆敷设船,该船已为该项目升级至7,000吨容量。

 

        据两家公司称,Taean电缆包将是LS Cable & System与LS Marine Solution继Shinan Ui海上风电项目之后,在韩国共同参与的第二大型海上风电项目。

 

        (本文版权归国际海事信息网所有,图片版权归原作者,转载请注明出处。)

 

The agreement reserves manufacturing capacity at LS Cable & System’s facilities and installation slots for LS Marine Solution’s cable-laying vessels (CLVs) ahead of the main contract. The companies aim to finalize the contract, including its value and other terms, by the end of 2026.

 

The two companies were selected as preferred bidders for the cable package in 2024, and are now carrying out engineering work and preliminary surveys to determine cable specifications and the scope of installation.

 

Taean Wind Power is a joint venture between Copenhagen Infrastructure Partners (CIP) and Vena Energy, which are developing the project that secured an offtake contract in the country’s 2024 wind power fixed-price auction.

 

In 2025, the developer also signed power purchase agreements (PPAs) covering 500 MW with Korea Western Power and Gangneung Eco Power.

 

Wind farm construction is scheduled to begin in the fourth quarter of 2026, with commercial operation targeted for the fourth quarter of 2029, according to previous project updates.

 

LS Marine Solution plans to deploy its GL2030 cable-laying vessel, which has been upgraded to a capacity of 7,000 tonnes for the project.

 

The Taean package will be the second large-scale offshore wind project in South Korea in which LS Cable & System and LS Marine Solution are participating together, following their work on the Shinan Ui offshore wind farm, according to the companies.